PAY! Quick Primer
FINAL PAYMENT
A 2002 survey revealed ASA's members rank "final
payment" as the most serious issue impacting the success of their
businesses. The issue of retainage and final payment is often a
situation where the leverage of the guy with the gold makes all the
rules.
-
Knowledge of final payment particulars is
important for subcontractors.
-
There are two different types of payments: 1) PROGRESS
PAYMENTS - periodic installments, usually on a pre-determined schedule
varying by calendar and project completion. 2) FINAL PAYMENT -
payment after your work has been completed and warranties have
commenced.
-
Retainage is pre-determined percentage withheld from
each progress payment, which is released on or about the time of final
payment.
-
For example, when the subcontractor is 99.9 percent
done with its work, the owner and general contractor only have paid 90
percent of the total cost.
-
Consequently, the owner has lots of leverage at the
end of the project, after substantial completion and occupancy of the
project, to force the sub to negotiate claims and perform extra
"punch list" work.
-
In fact, the owner and GC may have paid a lot less
than 90 percent of the amount due because of unapproved changes and
extras, further magnifying the leverage imbalance.
-
The owner claims that retainage is needed to ensure
that "punch list" items are completed. But the
leverage imbalance allows the owner to pile on extra "punch
list" items, sometimes called a "rolling punch list."
-
The most problematic causes of delays in payment are: approving
change orders, completing punch lists, dealing with a rolling punch
list and obtaining closeout documents.
WHAT ARE THE SOLUTIONS?
-
EDUCATION! The more you understand, the safer your
business is.
-
Establish a date certain for final payment, 30 days
after completion of work.
-
Ask for as much information as possible UP FRONT that
will help you assert lien and bond rights for unpaid work.
-
Document all out of contract work, approved written
change orders.
-
Refuse to work without written signed changed orders.
-
Use ASA's Generic Subcontract Addendum, which
is available in the Members-Only section of the ASA Web site.
-
Another valuable service for researching final payment
practices is the ASAC Business Practices Interchange located in the
Members-only section on this Web site and the ASA National Business
Practices Interchange found in the Members-only section of the ASA Web
site, www.asaonline.com.
CONCLUSION
(c) 2003 American Subcontractors
Association, Inc. ASA chapters have permission to reproduce this
article in all media. All other rights are reserved. |