Specialty
Trade Associations Council (STAC)
The
ASAC coordinates the activities of the STAC
(Specialty Trade Associations Council). STAC is a group of independent trade
associations:
-
American
Subcontractors Association of the Carolinas
-
American
Fire Sprinkler Association of the Carolinas
-
Carolinas
Roofing & Sheet Metal Contractors Association
-
Mechanical
Contractors Association of SC
-
Metrolina
Wall & Ceiling Association
-
NC
Association of Electrical Contractors
-
NC
Heating & AC Contractors Association
-
Painting
& Decorating Contractors of America
-
Steel
Erectors Association of America
-
Waterproofing
Contractors Association Inc.
Chair:
Tommy Parker, Parker Marine Contracting, Charleston, SC
Vice
Chair NC: Robert Roberson, David Allen
Company, Raleigh, NC
Vice Chair SC:
Timmy McLaughlin, Austin
Construction, Summerville SC
Secretary/Treasurer:
Linda Burkett, ASAC
Asst.
Treasurer: Dottie Nagle, CRSMCA
The
purpose of STAC is to identify problem areas within the industry which might
properly be affected by legislative or political action and to pursue such
action for the common betterment of its members.
The
implementation of the above purpose is pursued through voluntary action of
individual member associations, as well as through lobbyists, acting on behalf
of the member associations, in accordance with accepted procedural guidelines.
Such actions may consist of the following:
-
Investigation
and research directed towards the development of legislation and governmental
programs.
-
Education
of legislators, public officials and political candidates about specialty
contractor problems.
-
Direct
communication with legislative, governmental and quasi governmental officials at
any level of government.
-
Influencing
the electoral and political appointment process through education, and by making
recommendations to its individual members regarding campaign activities and
political contributions.
-
Education
of specialty contractors about legislation and the political process.
-
Coordination
with other industry groups regarding legislation and political affairs.
-
Filing a
friend-of-court briefs and similar court documents toward the end of achieving
favorable court decisions.
Following is a summary of some of the more important statutory enactments
and changes which STAC, with the help of other associations, has spearheaded in SOUTH
CAROLINA.
RETAINAGE REFORM - SC 365 - Amended existing section of SC
Consolidated Procurement Code regarding withholding of retainage on state
construction contracts and subcontracts from 5% to 3.5%.
BID LISTING ON STATE WORK (SC
Code 11-35-3020 (2) (b)) - The subcontractors successfully lobbied a major
package of protections in connection with the passage of the Consolidated
Procurement Code in 1981. The most
important was bid listing. A prime
contractor on state work is required to list each subcontractor who will perform
work of a value over three percent of the estimated cost of construction as
determined by the project architect. The contracting agency will identify by specialty, in the bid
documents, the subcontractors required to be listed.
ELIMINATION OF RETENTION ON STATE WORK (SC Code 11-35-3030 (4)) - Also in context of the Procurement Code,
retention reform was achieved. Retention
on state work is limited to 5% and must be released on a line-item basis.
A prime contractor must promptly pass such released retention on to his
subcontractors.
STATE DISPUTE PROCEDURES AVAILABLE
TO SUBCONTRACTORS/SUPPLIERS (SC Code 11-35-4210 (1)) - Under the SC Procurement Code, a
subcontractor/supplier who is “aggrieved in connection with a bid award of
solicitation,” may lodge a bid protect. In
addition, a subcontractor/supplier may apply to the Chief Procurement Officer
for Construction (State Engineer) for “resolution of a contract
controversy,” when the applicant is the “real party in interest.”
These provisions are unique to South Carolina.
INTEREST AND ATTORNEY’S FEES RECOVERABLE WHERE PAYMENT CLAIM
UNREASONABLY DENIED (SC Code
27-1-15)) - STAC successfully achieved the passage in 1986 of a statute of
inestimable significance. A
subcontractor or supplier who places by certified mail a claim for payment for
services or materials incorporated into the work, may recover interest and
attorney’s fees if the claim is not properly investigated, and, if valid, paid
within 45 days of the demand.
CONTRACT CLAUSES TRANSPORTING DISPUTES BEYOND STATE BOUNDARIES FOR
RESOLUTION ARE UNENFORCEABLE SC
Code 15-48-10 et seq.) - Many of the subcontract forms commonly used in South
Carolina by out-of-state general contractors require that the subcontractor go
back to the general contractor's home state to resolve a payment dispute.
Under a statute introduced through the efforts of STAC in the late
80’s, such clauses are no longer enforceable, and subcontractors may sue or
seek arbitration as otherwise provided by South Carolina law and the Rules of
Arbitration.
LIENS OF SUBCONTRACTORS AND SUPPLIERS ON CONTRACT PRICE
(SC Code 29-7-10 et seq.) - At the instance of the subcontracting industry
working through STAC, this statute was amended in 1991 to provide that a prime
contractor may not withhold funds from a subcontractor on one project for
alleged deficiencies on another project. To
withhold money on the same project, the prime contractor must declare such
withholding in its payment application to the owner and provide a copy to the
affected subcontractor. The fines
chargeable for diversion of money from a construction job were increased.
Importantly, the amendment rendered lien waivers unenforceable except to
the extent of payments actually made.
MECHANIC’S LIENS
(SC Code 29-5-10 et seq.) -In the early 90’s, the AGC filed an amendment
to the Mechanics Lien Statute which would practically destroyed the lien rights
of lower-tier subcontractors and suppliers.
The subcontractors came forward and extensive hearings and negotiations
took place resulting in the institution of a system where a lower tier provider
perpetuates its lien rights by sending to the general contractor a notice of
furnishing of labor and materials.
THE SOUTH CAROLINA PROMPT PAY ACT
(SC Code 29-6-10 et seq.) - STAC fought the AGC over prompt pay in North
Carolina for five years. When the
same bill was introduced in this state, the AGC decided to cooperate and a joint
effort produced a statute helpful to the entire industry.
This law requires prompt payment to contractors, subcontractors and
suppliers, and provides for interest penalties when payment is delayed.
The general contractor must pay the subcontractor within seven days from
the time the general contractor receives payment from the owner.
The subcontractors and suppliers within seven days of receipt by the
subcontractor of those funds.
THE SUBCONTRACTOR SUPPLIER’S
PAYMENT PROTECTION ACT -
“The Subcontractors and Suppliers Payment Protection Act” was
ratified in May of 2000. The Act renders pay-if-paid provisions unenforceable,
requires that payment bonds be used on all public projects in South Carolina,
and prohibits the issuance of payment bonds in South Carolina by other than
licensed insurance companies with a minimum Best rating of A- or B+ depending on
the circumstances. Moreover, no
subcontract clause will henceforth be enforceable which neutralizes any form of
payment protection created by statute or imposed by the project owner.
Provided by: Daniel T. Brailsford, Esq. of the Columbia South Carolina
law firm of Robinson, McFadden and Moore. Mr.
Brailsford has been active in
construction law for twenty years, representing the Subcontractors, Materialmen,
and Equipment Systems subcommittee of the ABA Forum on Construction.
He is General Counsel to the American Subcontractors Association of the
Carolinas and the Mechanical Contractors Association of South Carolina and
serves as legislative counsel to STAC. He
can be reached at 803 -227-1107
or by e-mail at dan@robinsonlaw.com.
|