GENERAL ASSEMBLY OF NORTH CAROLINA
SESSION
2007
S
4
SENATE BILL 1245*
Commerce, Small Business and Entrepreneurship
Committee Substitute Adopted 5/1/07
House Committee Substitute Favorable 7/19/07
House Committee Substitute #2 Favorable 7/26/07
|
Short Title: Retainage Payments/Construction Contracts. |
(Public) |
|
Sponsors: |
|
|
Referred to: |
|
|
|
|
|
March 26,
2007
A BILL TO BE ENTITLED
AN ACT amending the laws related to retainage
payments on Public construction contracts.
The General Assembly of North
Carolina enacts:
SECTION 1.
G.S. 143‑134.1 reads as rewritten:
"§ 143‑134.1. Interest on final
payments due to prime contractors; payments to subcontractors.
(a) On all public
construction contracts which are let by a board or governing body of
the State government or any political subdivision thereof, except
contracts let by the Department of Transportation pursuant to G.S. 136‑28.1,
the balance due prime contractors shall be paid in full within 45
days after respective prime contracts of the project have been
accepted by the owner, certified by the architect, engineer or
designer to be completed in accordance with terms of the plans and
specifications, or occupied by the owner and used for the purpose
for which the project was constructed, whichever occurs first.
Provided, however, that whenever However, when the
architect or consulting engineer in charge of the project determines
that delay in completion of the project in accordance with terms of
the plans and specifications is the fault of the contractor, the
project may be occupied and used for the purposes for which it was
constructed without payment of any interest on amounts withheld past
the 45 day limit. No payment shall be delayed because of the failure
of another prime contractor on such the project to
complete his contract. Should final payment to any prime contractor
beyond the date such the contracts have been certified
to be completed by the designer or architect, accepted by the owner,
or occupied by the owner and used for the purposes for which the
project was constructed, be delayed by more than 45 days, said
the prime contractor shall be paid interest, beginning on
the 46th day, at the rate of one percent (1%) per month or fraction
thereof unless a lower rate is agreed upon on such the
unpaid balance as may be due. In addition to the above final
payment provisions, periodic payments due a prime contractor during
construction shall be paid in accordance with the provisions of
this section and the payment provisions of the contract
documents that do not conflict with this section, or said
the prime contractor shall be paid interest on any
such unpaid amount at the rate stipulated above for delayed
final payments. Such The interest shall begin on the
date the payment is due and continue until the date on which payment
is made. Such The due date may be established by the
terms of the contract. Funds for payment of such the
interest on state‑owned projects shall be obtained from the current
budget of the owning department, institution, or agency. Where a
conditional acceptance of a contract exists, and where the owner is
retaining a reasonable sum pending correction of such the
conditions, interest on such the reasonable sum
shall not apply.
(b) Within seven days of
receipt by the prime contractor of each periodic or final payment,
the prime contractor shall pay the subcontractor based on work
completed or service provided under the subcontract. Should
If any periodic or final payment to the subcontractor be
is delayed by more than seven days after receipt of
periodic or final payment by the prime contractor, the prime
contractor shall pay the subcontractor interest, beginning on the
eighth day, at the rate of one percent (1%) per month or fraction
thereof on such the unpaid balance as may be due.
(b1)
No retainage on periodic or final payments
made by the owner or prime contractor shall be allowed on public
construction contracts in which the total project costs are less
than one hundred thousand dollars ($100,000). Retainage on periodic
or final payments on public construction contracts in which the
total project costs are equal to or greater than one hundred
thousand dollars ($100,000) is allowed as follows:
(1)
The owner shall not retain more than five
percent (5%) of any periodic payment due a prime contractor.
(2)
When the project is fifty percent (50%)
complete, the owner, with written consent of the surety, shall not
retain any further retainage from periodic payments due the
contractor if the contractor continues to perform satisfactorily and
any nonconforming work identified in writing prior to that time by
the architect, engineer, or owner has been corrected by the
contractor and accepted by the architect, engineer, or owner. If the
owner determines the contractor's performance is unsatisfactory, the
owner may reinstate retainage for each subsequent periodic payment
application as authorized in this subsection up to the maximum
amount of five percent (5%). The project shall be deemed fifty
percent (50%) complete when the contractor's gross project invoices,
excluding the value of materials stored off‑site, equal or exceed
fifty percent (50%) of the value of the contract, except the value
of materials stored on‑site shall not exceed twenty percent (20%) of
the contractor's gross project invoices for the purpose of
determining whether the project is fifty percent (50%) complete.
(3)
A subcontract on a contract governed by
this section may include a provision for the retainage on periodic
payments made by the prime contractor to the subcontractor. However,
the percentage of the payment retained: (i) shall be paid to the
subcontractor under the same terms and conditions as provided in
subdivision (2) of this subsection and (ii) subject to subsection
(b3) of this section, shall not exceed the percentage of retainage
on payments made by the owner to the prime contractor. Subject to
subsection (b3) of this section, any percentage of retainage on
payments made by the prime contractor to the subcontractor that
exceeds the percentage of retainage on payments made by the owner to
the prime contractor shall be subject to interest to be paid by the
prime contractor to the subcontractor at the rate of one percent
(1%) per month or fraction thereof.
(4)
Within 60 days after the submission of a
pay request and one of the following occurs, as specified in the
contract documents, the owner with written consent of the surety
shall release to the contractor all retainage on payments held by
the owner: (i) the owner receives a certificate of substantial
completion from the architect, engineer, or designer in charge of
the project; or (ii) the owner receives beneficial occupancy or use
of the project. However, the owner may retain sufficient funds to
secure completion of the project or corrections on any work. If the
owner retains funds, the amount retained shall not exceed two and
one‑half times the estimated value of the work to be completed or
corrected. Any reduction in the amount of the retainage on payments
shall be with the consent of the contractor's surety.
(5)
The existence of any third‑party claims
against the contractor or any additive change orders to the
construction contract shall not be a basis for delaying the release
of any retainage on payments.
(b2)
Full payment, less authorized deductions,
shall also be made for those trades that have reached one hundred
percent (100%) completion of their contract by or before the project
is fifty percent (50%) complete if the contractor has performed
satisfactorily. However, payment to the early finishing trades is
contingent upon the owner's receipt of an approval or certification
from the architect of record or applicable engineer that the work
performed by the subcontractor is acceptable and in accordance with
the contract documents. At that time, the owner shall reduce the
retainage for such trades to five‑tenths percent (0.5%) of the
contract. Payments under this subsection shall be made no later than
60 days following receipt of the subcontractor's request or
immediately upon receipt of the surety's consent, whichever occurs
later. Early finishing trades under this subsection shall include
structural steel, piling, caisson, and demolition. The early
finishing trades for which line‑item release of retained funds is
required shall not be construed to prevent an owner or an owner's
representative from identifying any other trades not listed in this
subsection that are also allowed line‑item release of retained
funds. Should the owner or owner's representative identify any other
trades to be afforded line‑item release of retainage, the trade
shall be listed in the original bid documents. Each bid document
shall list the inspections required by the owner before accepting
the work, and any financial information required by the owner to
release payment to the trades, except the failure of the bid
documents to contain this information shall not obligate the owner
to release the retainage if it has not received the required
certification from the architect of record or applicable engineer.
(b3)
Notwithstanding subdivisions (2) and (3) of subsection (b1) of
this section, and subsection (b2) of this section, following fifty
percent (50%) completion of the project, the owner shall be
authorized to withhold additional retainage from a subsequent
periodic payment, not to exceed five percent (5%) as set forth in
subdivision (1) of subsection (b1) of
this section, in order to allow the owner to retain two and one‑half
percent (2.5%) total retainage through the completion of the
project. In the event that the owner elects to withhold additional
retainage on any periodic payment subsequent to release of retainage
pursuant to subsection (b2) of this section, the general contractor
may also withhold from the subcontractors remaining on the project
sufficient retainage to offset the additional retainage held by the
owner, notwithstanding the actual percentage of retainage withheld
by the owner of the project as a whole.
(b4)
Neither the owner's nor contractor's
release of retainage on payments as part of a payment in full on a
line‑item of work under subsection (b2) of this section shall affect
any applicable warranties on work done by the contractor or
subcontractor, and the warranties shall not begin to run any earlier
than either the owner's receipt of a certificate of substantial
completion from the architect, engineer, or designer in charge of
the project or the owner receives beneficial occupancy.
(b5)
The State or any political subdivision of
the State may allow contractors to bid on bonded projects with and
without retainage on payments.
(b6)
Nothing in subsections (b1), (b2), (b3),
and (b4) of this section shall operate to prevent any agency or any
political subdivision of the State from complying with the
requirements of a federal contract or grant when the requirements of
the federal contract or grant conflict with subsections (b1), (b2),
(b3), or (b4) of this section. Each bid document must specify when
federal preemption of this section shall apply.
(c)
The percentage of retainage on payments
made by the prime contractor to the subcontractor shall not exceed
the percentage of retainage on payments made by the owner to the
prime contractor. Any percentage of retainage on payments made by
the prime contractor to the subcontractor that exceeds the
percentage of retainage on payments made by the owner to the prime
contractor shall be subject to interest to be paid by the prime
contractor to the subcontractor at the rate of one percent (1%) per
month or fraction thereof.
(d) Nothing in this section
shall prevent the prime contractor at the time of application and
certification to the owner from withholding application and
certification to the owner for payment to the subcontractor for
unsatisfactory job progress; defective construction not remedied;
disputed work; third party claims filed or reasonable evidence that
claim will be filed; failure of subcontractor to make timely
payments for labor, equipment, and materials; damage to prime
contractor or another subcontractor; reasonable evidence that
subcontract cannot be completed for the unpaid balance of the
subcontract sum; or a reasonable amount for retainage not to exceed
the initial percentage retained by the owner.
(e)
Nothing in this section shall prevent the owner from withholding
payment to the contractor in addition to the amounts authorized by
this section for unsatisfactory job progress, defective construction
not remedied, disputed work, or third‑party claims filed against the
owner or reasonable evidence that a third‑party claim will be filed."
SECTION 2.
This act becomes effective January 1, 2008, and applies to contracts
entered into on or after that date.
Signed into law: August 17,
2007